CommunityFeaturedTop Story

Paradise approves upgrades to wastewater treatment software

By Mark Squibb

Ahead of a massive rehaul of the St. Thomas Line Wastewater Treatment Plant to bring the plant into compliance with federal effluence regulations, the plant’s Supervisory Control and Data Acquisition (SCADA)software will be updated.

“The existing SCADA system at the St. Thomas Line Wastewater Treatment Plant is obsolete, and requires upgrading,” explained councillor Erin Furlong during a committee of the whole meeting. “Replacement of the SCADA system is part of the overall scope of the wastewater treatment plant project, but due to the existing software being obsolete, staff is recommending replacing the software now ahead of major construction.”
Staff had requested quotes for the supply and installation of a suitable SCADA system, and GIP Technical Solutions Ltd. submitted the lone bid of $56,694 plus HST.

“This is pretty straightforward,” said Furlong. “We did have some conversations about the SCADA system upgrade in the past and it’s just nice to see that we’re moving forward with the wastewater treatment plant project.”

Council later approved the purchase during a regular public meeting.

The overhaul of the treatment plant was initially valued at about $45 million. In 2021, the Town received $18 million in federal government funding for the project leaving the Province and the Town on the hook for the remaining costs.

A subsequent evaluation projected the upgrades at about $50 million. The Town has since broken the project into phases in hopes of securing additional government funding.

In 2022, the Town hired RV Andersen to oversee the project at a cost of $1.5 million.

The federal government is asking that upgrades be completed by 2040.