CommunityFeaturedTop Story

Holyrood asks Province to help fund water and sewer upgrades

By Mark Squibb

Holyrood is asking the provincial government for $2 million worth of new water infrastructure and $3 million worth of sewer upgrades.

“Council and staff reviewed our infrastructure needs and took into consideration our recent water issues and the continuing upgrade of the sewer system,” said councillor Steve Winsor. “The Town is continuing the path of improving these two areas to ensure safe, reliable and continuous service of both water and sewer.”

Winsor put forward two motions to apply for the funding, both of which were approved by council during its October 20 public meeting.

The first was to apply for $2 million to upgrade curb stops, shut off valves, flow meters, well pumps, failing pipes and address the lack of an appropriate GIS system to improve the water system.

Mayor Laura Crawley said the water outage this past August was proof Holyrood needs to update its system.

The second motion was to apply for $3 million for the installation of a blivit system. That’s an ‘all-in-one’ sewage treatment plant that processes raw sewage into a safe effluent.

That follows on a complete clean out of the sewer plant this past year, eliminating a stink that had haunted the area around it for years.

The Town has secured funding for further work at the treatment plant, but Winsor said it is at the mercy of suppliers and ensuring government compliance, and so the project has not advanced at the pace council hoped.

“When the plant phase is complete there will still be a need for treatment of the overflow not treated by the plant and this proposal submitted under our new 2026 MCW (Multiyear Capital Works application) will address that issue – bringing the town to a point where there will no longer be a need to bypass a cleansing system,” said Winsor. “This project will install three blivits to capture the overflow material and treat it using UV (ultraviolet light) and other systems.”

Mayor Crawley noted added that once the system is complete, Holyrood will be one of the few towns in the province that meets federal sewage guidelines.

Holyrood is looking for a 90/10 split on funding the work with the Province paying the bigger share. The Town would be on the hook for $200,000 and $300,000 respectively for the two projects. Council has borrowed a combined $500,000 from the Royal Bank at a fixed five-year rate of 5.23 percent to cover its portion. The loans will be reflected in the 2028 budget, not the 2027 budget, as the work will be undertaken in 2028.

“We don’t want to be borrowing money all the time,” said Winsor. “We don’t plan on taking out any new loans in the upcoming budget cycle. But what I’ll say is this town council has made a lot of effort over the last few years to pay off previous loans. We’re in a very strong fiscal position and this is an excellent return on invest.”

Winsor said Holyrood would not be able to complete the projects without government funding.

Leave a Reply

Your email address will not be published. Required fields are marked *