Council eyeing a return to Paradise Town Hall early in new year

By Mark Squibb

Paradise council has approved a third change order for the reconstruction of the town hall as the cost creeps up and the clock ticks down toward a reopening anticipated early in the new year.

A fire that began in a town dump truck gutted both the town hall and adjacent depot in February 2025, forcing the closure of both buildings.

Rather than rebuild the town hall as it was, council opted to update it to make it more functional and hired BELFOR to undertake the project for $3.36 Million, HST included.

In July, council approved a change order of $553,538, HST included, over the initial contract for a revised floor plan, demolition of the depot (floor slab excluded), an upgrade of the interior partition wall between the depot and town hall, additional windows and doors, and the elimination of a stairwell.

A second change order of $48,916, HST included, was approved in September. That covered additional work to complete the depot demolition, modifications to exterior doors, and testing of the rooftop HVAC units to see if they were still functional after the fire.

The third change order, approved last month, comes to $97,477, HST included. The work includes reconstruction of an exterior wall and additional electrical work to provide in floor power and data connections.

“During exploratory work, including the cutting of test pits in the concrete slab, it was discovered that the existing wall did not have footings,” explained councillor Erin Furlong. “As a result, additional work is required to provide necessary structural support and ensure the wall meets building code requirements for an exterior wall.”

The changes push the town hall reconstruction cost to $3,524,206, plus HST.

WSP E&I Canada Ltd., meanwhile, was awarded the job of designing and building the new depot for $550,633, HST included. It will be located between McNamara Drive and the Dianne Whalen Complex.

Council had budgeted $3 million for the town hall project and $800,000 for the depot demolition and construction.

Councillor Glen Carew asked if additional work above and beyond the three change orders might push the project overbudget.

Furlong said there is no way of knowing if there will be more change orders, but barring any additional work, the project should wrap up under budget. Both the town hall and depot are scheduled to be completed by December 31.

“So, potentially, the first meeting of the new year will be in the new chambers,” said Mayor Patrick Martin.